Model 3: Hydro Power Plant Pumping and Releasing Optimization Problem
Based on the previous pumping problem in Model 2, the optimization model could be further improved by
involving releasing operation in it. Figure 3 shows the pumping and releasing optimization during available
time.
Upper reservoir of the
Power grids
hydro power plant
Capacity of
Turbine and generator: releasing process p
the reservoir
00000
@@@@@@@
Initial stored
energy Ein
Turbine: Pumping process p+
Figure 3 Pumping and releasing process of a hydro power plant
The mathematical model of the pumping and releasing process of the hydro power plant is formulated as
follows:
Min
(5)
(6)
Subject to
(7)
(8)
0,
(9)
ts St /MWh)
Time
17
18
24
21
22
23
19
20
6.8
17.4
18.9
16.4
17.5
17.3
9.5
7.5
Price($/MWh)
Table 2 Hydro power plant information
2
Start time
ts
22
End time
te
6.4 MWh
Initial energy stored in the upper reservoir
Eini
60 MWh
Target energy stored in the upper reservoir
Etar
E
64 MWh
Capacity of the upper reservoir
P Pump
12 MW
Maximum pumping power of the pump
16 MWh
PG&T
Maximum generation power of the generator
Not the question you are looking for? Ask here!
Enter question by text
Enter question by image
Unlock Smarter Learning with AskSia Super!
Join Super, our all-in-one AI solution that can greatly improve your learning efficiency.